Achievements
100,000 Sqft Industrial Building for Propel Industries
Project Overview
- Client: Propel Industries Private Limited
- Project Type: Industrial / Commercial – Pre-Engineered Building (PEB)
- Location: Coimbatore, Tamilnadu.
- Total Built-Up Area: 100,000 Sqft
- Completion Time: 90 Days
Scope of Work
- Design, fabrication, and erection of the Pre-Engineered Building
- Structural Fabrication using MS plates for primary members
- Installation of secondary members, including GI purlins, roof sheets, and cladding sheets.
- Integration of advanced shearing machine with 16mm capacity and 6.5m length for precise steel cutting.
- Ensuring quality control and compliance with industry safety standards
Challenges & Solutions
- Tight Deadline: Project successfully delivered in 90 days with efficient planning and execution strategies.
- Material Handling: Used advanced fabrication to optimize steel cutting and reduce waste.
- Weather Conditions: Applied contingency plans for smooth, uninterrupted progress.
Key Achievements
- Rapid Execution: Industry-leading speed for the completion of a 100,000 Sqft industrial building.
- High-Quality Fabrication: Used advanced machinery and precise engineering for a durable structure.
- Cost Efficiency: Optimized materials and labor for the best return on investment.
1,100-Ton PEB Project for Southern Railways, Trichy
Project Overview
- Client: Southern Railways
- Project Type: Pre-Engineered Building (PEB) – Industrial
- Location: Trichy, Tamil Nadu
- Total Steel Fabrication: 1,100 Tons
- Project Purpose: Coach Maintenance Shed with a Two-Layer Platform on Both Sides
Scope of Work
- Structural Fabrication & Erection of a large-scale coach maintenance shed for Indian Railways.
- Engineering and Design to support heavy-duty railway operations.
- Two Layer Platform Construction for efficient accessibility and maintenance workflow.
-
PEB Structural Members & Secondary Members Installation, including:
MS Plate Fabrication for Primary Members
GI Purlins, Roof Sheets, and Cladding Sheets - Precision Shearing & Cutting using 16mm capacity shearing machine (6.5m length).
- Strict Adherence to Indian Railways Standards for durability and safety.
Challenges & Solutions
- Precision in Structural Design: Ensured heavy-load bearing capacity with optimized engineering for robust railway operations.
- Tight Project Timeline: Efficient fabrication and erection planning helped complete the project on schedule.
- Logistics & Material Handling: Coordinated transportation of 1,100 tons of steel while minimizing wastage.
Key Achievements
- Successful Completion of One of the Largest Railway PEB Projects
- 1,100 Tons of Steel Fabricated & Installed Efficiently
- Enhanced Coach Maintenance Operations with Multi-Layer Platform
- Met Stringent Quality and Safety Requirements of Southern Railways
210,000 Sqft Garments Factory for Victus Apparel Pvt Ltd
Project Overview
- Client: Victus Apparel Private Limited
- Project Type: Garments Factory – Office Block & Utility Buildings
- Location: Tirupur
- Total Built-Up Area: 210,000 Sqft
- Project Duration: 8 Months (Fabrication & Erection)
Scope of Work
-
Design, Fabrication, and Erection of a large-scale garments factory including:
Main Office Block
Mezzanine Floor Construction for expanded workspace
Utility Buildings (Warehouses, Production Halls, etc.) - Structural Fabrication Using PEB Technology for optimized cost and durability
- Precision Engineering & Shearing using advanced machinery with a 16mm capacity and 6.5m shearing length
-
Installation of Secondary Members, including:
GI Purlins, Roof Sheets, Cladding Sheets - Seamless Execution & Timeline Adherence ensuring zero disruptions to client operations
Challenges & Solutions
- Large-Scale Execution in a Limited Timeline
- Efficient fabrication and erection strategies ensured completion within 8 months.
- Multi-Structure Coordination.
- Designed and executed separate buildings while maintaining uniform quality and standards.
- Material Handling & Logistics
- Optimized procurement and steel fabrication planning for minimal waste and cost efficiency.
Key Achievements
- Completed a 210,000 Sqft Industrial Facility in Just 8 Months
- Integrated Mezzanine Floor for Space Optimization
- High-Quality PEB Construction for Durability & Cost-Effectiveness
- Utility Buildings Designed for Maximum Operational Efficiency